Risk Register

A project risk register is a tool project managers use to track and monitor any risks that might impact their projects. Risk management is a vital component of project management because it's how you proactively combat potential problems or setbacks.



Risk Description

Impact

Risk Response

Risk Level

Risk Owner

Automation Testing Software licence delay

Delay in starting testing and project schedule impact

As we have one licence. Planned to start automation testing in 2 shifts. Planned to get one more licence in 2 weeks’ time.

High

IT team

Frequent Disruption in dependency API services

Delay in development of integration and unit testing

Dependency API service is down, and the team is working on resolving the issue. Continuously working with API team

High

External Team/ Project Manager

There is chance of new requirement or scope change expected

Impact in Plan

Start with a well-defined project scope and project plan should clearly articulate the work that will be done with milestones and metrics.

Medium

Project Manager

Change review board (CRB) un-availability

Impact in starting the change without approval of the approach.

Use standard changes, Use deadlines and automated reminders.

Try to revise the CRB team.

Medium

Project Manager

Quality Risks from developers and testers

Impact in quality delivery

Having a well-prepared testing plan makes a product be more competitive and assure the products coming in a predictable timeline associated with high quality.

Medium

Project Manager

  

Comments

Popular posts from this blog

Scaled Agile Framework (SAFe)

The Scaled Agile Framework (SAFe) is a set of organizational and workflow patterns for implementing agile practices at an enterprise scale. The framework is a body of knowledge that includes structured guidance on roles and responsibilities, how to plan and manage the work, and values to uphold. Scrum is a simple, flexible approach to adopting Agile that's great for small teams. SAFe is an enterprise-wide Agile framework designed to help bring Agile beyond the team and into the company as a whole. Scaled Agile has built a comprehensive level that includes all the four layers called the team, program, large solutions, and portfolio level. 4 Layers: Portfolio - Strategy, Vision, Roadmap, Strategy goal, Decision making, Budget, Portfolio level metrics,  Program - Align multiple teams towards a common mission, Bring together all the Agile teams, transparency, collaboration, and synchronisation, Scrum of Scrums, Product Owners to define the overall vision. Large Solutions - archite

Lessons learned from sprint retrospective meeting

Scenario: Team Missed Sprint Goals Challenge: A development team consistently missed its sprint goals, leading to frustration and a drop in morale. Team members felt overwhelmed by the workload and struggled to communicate effectively. Retrospective Insights: During the retrospective, team members openly discussed their challenges and frustrations. They identified bottlenecks in communication, unclear priorities, and unrealistic expectations. The team realized that individual workloads were not evenly distributed, causing burnout for some members. Lessons Learned: Effective Communication Matters: The team recognized the importance of clear communication. They committed to regular stand-up meetings, where everyone shared progress, blockers, and priorities. Balancing Workloads: The retrospective highlighted the need to distribute tasks more evenly. They decided to monitor workloads and adjust assignments accordingly. Setting Realistic Goals: The team acknowledged that setting achievable