Planned Value = (Planned % Complete) X BAC (Budget at Completion)
Example:
Project cost (BAC): 100,000 USD
Project duration: 12 months
Time elapsed: 6 months
Percent complete: 50% (as per the schedule)
= 50% of BAC
= 50% of 100,000
= (50/100) X 100,000
= 50,000 USD
Therefore, the project’s Planned Value (PV) is 50,000 USD.
Earned Value = % of completed work X BAC (Budget at Completion)
Example:
Project cost (BAC): 100,000 USD
Project duration: 12 months
Time elapsed: 6 months
Percent complete: 40% (as per current status)
= 40% of BAC
= 40% of 100,000
= (40/100) X 100,000
= 40,000 USD
Therefore, the project’s Earned Value (EV) is 40,000 USD.
If the project going in same trend it will take 3 months additional timeline to complete the project.
There is no special formula to calculate the Actual Cost. It is an amount that has been spent, and you can find it easily in the question.
Example of Actual Cost (AC)
You have a project to be completed in 12 months. The budget of the project is 100,000 USD.
Six months have passed, and 60,000 USD has been spent, but on closer review, you find that only 40% of the work has been completed so far.
The Actual Cost is the amount of money that you have spent so far. You have spent 60,000 USD on the project so far.
Hence,
The project’s Actual Cost is 60,000 USD.
Comments
Post a Comment