If the $1,000,000 revenue was only delayed by 3 months and the client eventually paid the full amount, then:
Accounting Profit & Loss
There is no direct profit or loss from the delay itself.
Example:
Contract Revenue = $1,000,000
Project Cost = $800,000
Profit = $200,000
Even though payment arrived 3 months late, the final profit remains $200,000.
Cash Flow Impact
The real impact is on cash flow, not profit.
For 3 months:
Accounts Receivable = $1,000,000
Cash not received = $1,000,000
Company may need to use reserves or borrow money to pay salaries, vendors, and cloud costs.
If Borrowing Was Required
Suppose:
Revenue delayed = $1,000,000
Annual interest rate = 12%
Delay = 3 months
Interest cost:
1,000,000 \times 12\% \times \frac{3}{12}
= 30,000
Interest expense = $30,000
Then:
Original Profit = $200,000
Interest Cost = $30,000
Actual Profit = $170,000
Program Manager / PMO Reporting
You would typically report:
Schedule Variance: 3 months delay
Revenue Recognition Impact: $1,000,000 deferred by one quarter
Cash Flow Impact: Negative $1,000,000 for 3 months
Profit Impact: Nil (unless financing costs, penalties, or additional delivery costs were incurred)
A common executive statement would be:
> "The project experienced a 3-month milestone delay, resulting in a $1M revenue recognition shift to the next quarter. While overall project profitability remained unchanged, cash flow was adversely impacted during the delay period."
This distinction—profitability vs. cash flow—is important in Program Manager, PMO, and P&L discussions during interviews.
Comments
Post a Comment